|
091112 - Al M. was down at the
cans today, waterproofing the roof. He did an awesome job.


I'm willing to bet that this will be
watertight! Al also picked up a wack of Roxul insulation.
Steve didn't show up today - so I am looking at bringing in some more
resources to get caught up tomorrow
091111 - Take two - here are the
pictures from yesterday - put up this morning

The main Coax and network cable transfer
between the two C cans


South Can - Ceiling with the Core line
run

Bill's workstation - coax, power, network
drops, 12 volt and 24 volt power drops


North Can - insulated and vapour barrier
on the ceiling


Dennis - working the world from his car -
on one of our antennas
091111 - Steve worked down there
for the day today and got a lot of the insulation done. And I
forgot the camera at the cans. Ben came down late this afternoon,
and completed the grinding of the floor. He also cleaned up the
ladder welded to the door. Here is a picture from my car of Ben
using a cutoff wheel to clean up the ladder. Camera phone -
picture does suck! I'll push up the other pictures tomorrow.

Steve put in all of the insulation that
we had. The whole North can has had the ceiling insulated, and the
ceiling had the vapour barrier installed. The C cans were cleaned
up. Jeff and Al E. dropped by, and dropped a bunch more radio
'stuff' for the project. Jeff, who is an industrial electrician,
pointed out some things I needed to change (i.e. separate the high
voltage core lines from the low voltage core lines - whoops). the
place is really coming together. The kerosene heater is
helping out big time - we put some plastic in front of the open door,
and it was quite balmy in there at times!
Dennis dropped by earlier today, with his
7000 mounted in his car, and an auto-tuner. We put together a
quick patch cable, along with an end on the cable going out to the 80
meter dipole. Dennis had a blast, working stations through out
North America. Glad it worked for you Dennis - Drop by and 'plug
in' anytime.
091110 - I had Steve, a
contractor, in there for the day. He finished off all of the core
line that I had, and tied down most of the four inch electrical boxes.
Al showed up, after work, and pulled in most of the 12 and 24 volt
wiring. He also brought about six bags of Roxul insulation, 2x4 on
24 inch centers. They got a chunk of it in, and then started to
put up the vapour barrier. Steve also foamed behind each
electrical box, to isolate it from the steel outside of the C can.
Here are some pictures:

North Can - Coax transfer room - first
insulation going up, as well as vapour barrier.

12 and 24 volt wiring - the 24 volt
wiring is in the center - we'll put the AGM batteries under a seat,
along with a charger / inverter.

My workstation to the left

The 12 volt wiring back into the
electrical room - Al pulled all of this in this afternoon.

Looking East in the North can -
insulation is starting to go in.
091109 - Ben spent some time at
the cans today. He ground the side walls down on the South Can
(where we had opened up the two C cans in the center). He went
through all of the grinding wheels he had on doing the South side.
He had a good point, we should look at just knocking down the high
points on the North can, as we could use some leveling compound (after
we insulate and get some heat in there!) and avoid another couple of
hours of grinding. Here are some pictures:

Where there's sparks - there's Ben

The South side can ground down - Ben
indicated that it was incredibly strong steel and difficult to grind
through
I've given up on the idea of spray
insulation. I am getting quotes of $4.5K to $10K to do this - that
is way out of line with what I can justify. I think I am going to
go with Roxul Mineral Wool insulation, and then vapour barrier the
daylights out of it. Next steps are to finish pulling the core
line, then fix the boxes so they don't move (nail through them, screw
them down, etc). I will then insulate the ceiling of the first C
can, vapour barrier it, and then move the temporary lighting to the
center of that ceiling. I can then do the outside wall, and then
repeat on the other C can. We will then do the center walls, and
the two end walls.
We won't be doing the two doors - one
will have a sliding glass patio door in front of it (on the kitchen
side), and the other will have a seven foot patio, and then a sliding
glass door. I may have to rethink this - but that is the current
plan.
091107 - Spent the day at the site
today. Got there early. Al joined me for several hours, and
we got the first piece of coax pulled through the first four inch sewer
pipe. I knew the plan would work, I just didn't know how well.
Al had picked up a four inch squishy toy. We fastened the wire to
it, and then some string. Al started the blower, and holy cow, the
string just flew out of my hands.
We have over 2500 feet of Core-line run
already. Here are the first pictures of how they are being
terminated. There is huge pressure in the core-line - so it warps
the connector blocks. I can't find a way around it - so we might
have to live with it. It is more aesthetic than anything else.






Above - thanks Dave G. for the heat - it
helped a lot!

The pipes coming through the floor that
run to our hydro poles and future towers







North Can - coax, power, network transfer
station

North Can - Coax, network transfer
station


Electrical panel - South Can - West side
091103 - Had a contractor in there
yesterday and today for a few hours. He cleaned up a bit, and then
continued to run Core-line. We have used up all of the 1 inch and
the 1/2 inch. Only 3/4 inch left. Here is a picture - from a
camera phone so it isn't that clear.

Above is 'my' workstation location.
From left to right - network connection, 120 and 220 volt power
connections, and then four core-line pipes that will bring in Coax from
the coax transfer room. Each of the 1 inch pipes should allow two or
more coax lines to come in to the workstation.
The Coax Transfer room, also the
bathroom, is where all outside antennas will come into. They will
all terminate on a thin, 1/8 thick plate of aluminum, with a PL259
connected to a bulkhead connector. This will be grounded to the
station ground. Above this plate, will be a couple of other
aluminum plates. These plates will terminate the core-line - in
their various dimensions. From these core-line connectors will
hang the coax that goes to each workstation. Each individually
labeled coax line can then be patched to the appropriate antenna.
We will need to enforce some fairly
stringent change control to ensure that antennas are only removed or
changed with the full knowledge of the other station operators.
Over time, as we add more antennas, we will need to add some more
complex switching arrangements (i.e. remote coax switches).
The aluminum plates are worth a bit of a
story. I ordered them from Metal Mart - three inches deep, and as
wide as the space between the studs. I figured we would just drill
in or punch the holes to contain the core-line. When we laid it
out on Saturday, with Chris S., we realized how many holes we needed to
drill. I spoke with Ben L. on Monday, and he indicated that this
was not going to be a trivial task! I got some quotes and I was
floored. Ben suggested that I go to a fabrication shop that had a
computer operated plasma cutter or a water cutter. I have one
locally. I spent some time with the fabricator, and got a quote
for about $250 - or half of what it would cost to drill and / or punch
them.
In addition to the coax core-line
terminations, I also arranged for some extra ones for the power going to
the two electrical terminations. These would be screwed into the
studs, the core-line connected to them, and the electrical cables
hanging down from them to be terminated in the electrical panel.
Still to be worked out is how I do the DC
power distribution. We anticipate that the 12 volt power will be
on the top of the C cans - so we will jumper them some way between the
top of the can, and the power distribution panel. This will be the
liquid nicad batteries - outside and vented. The 24 volt power
system, the AGM batteries, will be in the office, under the resting
platform ;>}} 24 volts will be available to drive a UPS (for the
computers, maybe the solid state amplifier), and for a DC to DC
converter. We have 800 amp hours of wet cells for distribution to
the radios. We have almost 880 amp hours for 24 volts. In
addition, we have other wet cell battery technology to run the alarm
system, lighting, etc.
The 12 volt system will be floated off of
a 90 amp hour power supply that I have. Even with three stations
going, I doubt we are going to exceed that (if we have hydro power, or a
big enough generator). I don't currently have a 24 volt charger -
I will need to work on that. For the other 12 volt systems, Scott
S. has a charger that I am interested in - 45 amp hour if I remember
correctly. I also have a 30 amp hour charger in my jeep that I can
use for another battery bank.
091101 - Big weekend on the
project. Many hundreds of feet of core-line were installed.
This is plastic hose, which allows cables to be run through them in the
future. We are wiring the whole environment with this hose - so
that we can pull whatever cables we need in the future. I don't
have any pictures - but will take some and get them up shortly.
Here is one picture from Al - how the AGM batteries were wired together
- can't lose this...

I need to call Hydro tomorrow and see
about getting hydro power in there. I would like to finish off the
core-line and get the insulation in shortly. It is chilly in the
cans!
We were down there one night this week
-forget which night, and Ben welded the ladder to to the inside of the
door. It was a foul night - raining like crazy. Al moved the
welding unit with Baby Huey (the mini-excavator) and Ben did the welding
under less than idea conditions. We now have a ladder which is
accessible when the door is opened. I will take some pictures and
post them.
I have been listening to the bands -
awesome signals at this location. We only have an eighty meter
dipole up - and listening to the bands has been awesome. Big
signals - no noise floor.
091027 - I was down to the project
early this a.m. The excavating contractor wanted to be there
between 7:00 and 7:30 - so I was there at 6:30 a.m. Beautiful
clear morning - major storm clouds on the horizon - but stars aplenty.
1 degree centigrade - and the geese were migrating overhead. Once
again - beautiful morning. I spent most of the day working out of
the mobile office. The 2010 Ford Fusion Hybrid has a 16 speaker
surround sound system that is integrated via Bluetooth to my two phones.
In addition, I have high speed internet - so my office is my car on days
like today. Works big time. What follows are some pictures
of what went on the last couple of days.



























|