|
091211 - Randy was down at the
project today. He used some material to secure the door, and then
sealed it with foam and silicone. Here are some pictures.

We have a persistent drip between the
cans. We've done some significant work to try and make it go away,
and no go. So, plan B - we capture the water and move it outside
of the cans. We've split the four inch pipe in three.

These are the two ends - with spouts.
We will take any water that comes in and evacuate it through the side
walls

Hole drilled through the side walls - any
water will be 'flushed' out this way

Inside door, after it had been blocked
and siliconed

Trimming out the inside posts

From the outside, looking towards the
steel access door. Once the expanding foam had been added, along
with the silicone, it was amazing how the space retained heat better
than before. We had turned off the kerosene heater, because of the
dust as Randy was cutting, and it was comfortable in the shack an hour
later. It is really coming together. I will be in there this
weekend with some contractors, priming, painting, and moving forward
Got the quote from Hydro today - ouch -
$8K to bring power to the lot line - it is too much. I need to
look at alternative options
091208 - Randy was working at the
site again today. We met at Surrey New and Used, and picked up a
36 inch steel door. The door was installed today. In
addition, the Electrical room was finished with board, and so was the
Coax Transfer room. Things are moving along. Randy also did
a dump run, so the place is cleaned up again. Here are some
pictures:

Outside looking in - outer door open -
new wall, new door. I need to bring in some Baltic birch as
fillers to make sure the door is tight to the frame

Randy and I moved the AGM batteries
tonight - to their final resting place ;>}}
They were very heavy - but the dirty
floor helped a lot!

South Can - looking West

South Can - looking East - through the
Patio doors - bitterly cold - -9C this a.m.

North Can - looking East - Coax Transfer
room is finished off

North Can - looking West - insulated door
installed - needs to be blocked and insulated

Coax transfer station - all boarded -
extra power points installed
BC Hydro was down today - two poles, no
additional transformer required. On top of this, I have to supply
the pole (to a standard), and all of the necessary 'stuff' to connect to
it. I'm talking to Jeff to try and understand how big this is
going to be. The Hydro guy figured about $5K for installation to
the lot line! Not cheap, but over a ten year project, it might be
more than reasonable - need to look at the numbers.
091207 - Randy was at the site
working today. He finished off the security wall - double layer of
plywood - extra reinforced 2 x 6 construction, insulated with six inch
Roxul - vapour barrier. This should go a long way towards
improving the amount of heat we keep in the shack during the winter, as
well as significant improving our security. The intent is that we
would open up the main C can doors, and then there is a reinforced steel
door that still has to be opened, all while the timer is ticking on the
alarm system. The main C can door would be opened, and locked
open. There is a ladder on the inside of the door, which is used
to access the roof. There will be a plywood 'Do not climb' placard
on the ladder when it is not in use. Randy also got started on the
Coax Transfer room - with the ceiling in, along with part of the walls.

Above - The wall is now finished - ready
for the door. The door will be a solid core, steel clad door -
with at least one deadbolt - more than likely two. It will be a
substantial structure. in the summer we will add a screen door to
it, to allow air to flow through the shack.

This is standing at the gate, looking due
south. Hydro is coming down tomorrow for a look at the site.
You can just barely see the transformer about 100 yards down the road.

Al took a run at this part of the field
on Sunday. Freezing cold. We have swaled the field back away
from the road - trying to get the water from running through the road
bed. It appears to be looking good - but it is still freezing
cold. The frame has been welded to the roof, with isolation pads
to minimize the sound transfer. The pit that has our pipes from
the road was finished off, capped and the hole filled in again.
Ben was going to try and make it down
there today and weld in the pods - but had some personal commitments
that came up at the last minute. Randy is there tomorrow - ideally
installing the main door, finishing the Coax Transfer room, and then
starting the boxed in ceiling fixture thingy's!
091206 - I was back in there early
today - cleaned up and got ready for Jeff to come out to pull some more
electrical cable. It has been bitterly cold (well - by Vancouver
standards), and the place was cold this a.m. I got the big propane
heater going for 20 minutes - 40,000 plus BTU's of heat, and the place
started to warm up. I got the Kerosene heater working as well.
The wind was blowing from the East, and it blew through the open door
and the partially open patio door. I need to work on that this
week.
Kenny and Christian came over for the day
to work. Jeff unexpectedly had Jason, so we kept an eye on the
little guy. He went out to play some soccer, and Kenny checked on
him. I went out a minute or two later, and there was a big coyote
showing too much interest in Jason, so I had them come back in.
Christian was really good with Jason - and he had a little helper for
the afternoon. Judy brought down an excellent lunch.
We got a lot done - pulled more wire, and
Jeff got a good run at the panels. We ran out of ground wire
(green wire), so that was all we could pull today. Christian
helped with the wire pulling, and then went on to prime some more of the
two cans. Kenny worked on the 2 x 6 security wall - this is a wall
just inside the main can doors - solid construction, double plywood -
insulated. Here are some pictures:

Can you see how cold and windy this was?

It was a very cold and windy day today.
The East door was partially open so that the generator cables could be
fed in , and the wind was just howling in there. The patio door
let quite a bit of cold wind in - but the Kerosene heater did a pretty
decent job of keeping the place tolerable. We still have to seal
the area around the doors that let the wind and cold in behind the 2 x 4
insulated walls. It is on the list...

Christian and his little helper - Jason


Jeff - and those aren't all of the wires
that are going to get pulled - just where we got to today -Notice the
Christmas colours - Red, White and Green


Where we got to with the security wall -
there will be a 36 inch solid core steel door installed here. The
wall will be insulated, reinforced and alarmed - it should also be
warmer! The intention is that the outer door will be opened, and
locked open. The alarm will be tripped, and there will be x
seconds to get into the main building, and turn off the alarm. The
alarm will be audible, visual, with notifications over the internet, via
email, SMS and cell phone. In addition, the plan is to have
Internet feed with IP cameras monitored over the internet.
091205 - Saturday - went for the
Ham breakfast, and then to a paint store, picked up Kenny and Christian,
and headed to the project. We were there about 9:00 a.m. and got a
good day in there. Christian started with priming the Electrical
Room - I did some priming as well. Kenny fixed the
insulation in the Electrical 2 area, and then we put up the MDO panels.
In addition, in the freezing cold, Al worked on the road / field swale.
It was dark when I left so don't have pictures of that. Judy came
down about 2:45 today and did some priming as well. I had to take
a Change call at 3:00 that went a bit over an hour. Here are the
pictures from today.






091130 - Ben and Al were down at
the site today. They installed the top part of the ladder - much
safer now. They also installed the tubular platform to support the
two pods. It was quite the show getting them moved out of
the way, welding in the supports for the platform. Ben had some
good ideas on how to reduce the noise from the generator - a couple of
weeks will tell us how it is working.

It started out as a very nasty day -
cold, pouring down and miserable. Al's tent was useful.
Surprisingly, it turned nice later in the day


The platform - intended to spread the
load of the two pods across the support structure of the C can


A little jeep action

Throw a millwright and a plumber -
pipefitter together and they will work out some sort of a leverage
arrangement that will move something



Now that is a decent, safe ladder
We also moved the welder to the other
side of the C Cans - so that we can finish off the security wall at this
end
091129 - Was down at the site for
a few hours by myself on Sunday. Cleaned up a bit, got a station
set up. Dave 'The Big Easy' was in there on Saturday and pulled
two coax lines into each workstation, and then added connectors. I
used one of the two lines to hook up a radio and antenna tuner to the
only antenna we have up right now - the eighty meter dipole. I am
using the RigRunner 12 port, with an AGM 155 amp hour battery connected
to it. I ran for several hours on Sunday, along with my cell
plugged into the battery. I had a bridge up and a change going on
for several hours, so couldn't really operate, but I was warm, dry and
operational!
The battery went down to about 12.5
volts, but when I was back there this afternoon, the voltage was back up
to 12.7 volts. Oh yes, I turned off the generator for about an
hour, and ran off of one of my high intensity LED lights - see the
pictures below:



Electrical room - wall board complete
except for the last foot at the top - we'll leave that open until the
electrical is finished

This wall needs to be the next focus - We
ran out of Roxul insulation - welder is now moved - so we can also build
the security wall





Generator off, kerosene heater on,
battery power, LED lighting - nice
|