|
100509 - Went to the project
yesterday morning with Al - we had to drop off a countertop donated by
Gord K. Thanks Gord. Well;, guess what - we had some
condensation inside the power room - where the water would be pooling
above it. So - general consensus is that I need to pull the air
that is in the space between the walls and ceiling (which is insulated)
and circulate it to the outside. Dave G. suggested I go to a boat
place, where they have solar powered fans - one in each can should do
it.
100425 - Went down to the project
at about 1:15 today. Opened it up, let the air blow through it,
and fired up the generator. I was there about 2.5 hours.
Good opening into Europe - but didn't actually work anyone. Dave
Barber and his daughter dropped by and we had a nice visit in the
sunshine. So - my power room leak is still missing, but the leak
in the other C can - is back! Grrrrr.
Here are some updated pictures.








The brothers told me that the field would
self seed - and they were right. I'm surprised - but it is
working. The pad is very dry, and the field is starting to dry
out. Now if I could only figure out the leaks!
100421 - Went down to the project
this afternoon. It has been raining a lot lately, and I wanted to
check on my leak. Surprise - surprise - no water in the power
room. What the F***? Here are the pictures:

The ceiling - ripped out.
Dry-as-a-bone! What the heck? You can see that there was
water up there,
there is mold on the wood (I'll look at throwing some bleach up there
before I close it back in again.)
There was zero, nada, none, no water up there.



No water on the floor - on any of the
walls, or any where! I know I have a leak - I just can't
find the darn thing.

My messy workstation - see my call sign
on the right above the Broadcast Radio? Thanks Gary.

On the porch - the Roxul Mineral Wool
insulation - drying out - it was soaking wet.
100414 - Was down at the site
yesterday, and we pulled a section of the ceiling in the power room
down. We also cut out the plastic, and pulled down the soaking wet
Roxul mineral wool insulation. It was pretty wet up there.
The ceiling had a lot of moisture on it - beaded up and looking like
condensation. It likely is condensation, but there is definitely a
leak or two in there as well. I need to find the leak, fix it, and
then float something on the roof to keep water from pooling there in the
future.
The field is drying out, the pad is very
dry, and Al M. scored a urinal for the project - whooo hooo.
100326 - We had a big team working
on the Project last Sunday. We got the generator stand, and the
generator installed in one of the pods. We also put in two of the
pipes between the Electrical room and the pod. We have a third one
to finish - another weekend. We now have 120 Volt ac into the pod,
and out of the pod. We didn't get the actual propane plumbed in,
but we did jury rig a 20 pound tank to start with.
Ben had converted one of the man hatches
with louvers, but after running the generator with the door open a foot,
we will need a lot more ventilation if we are going to run the generator
with the door closed - and that is the plan. We are going to cut a
large hole in the floor, and then put ventilation screen over it.
I think we are going to need to put in a large fan and actually pull
warm air out of the pod. I also need to look for some muffler
cloth, as there is a lot of vibration and it is banging the pipe
against the hole we cut. The muffler cloth will also help to keep
the heat out of the pod that is radiating off of the muffler pipe.
100316 - Worked from the Project
today. It was slow on the work front, and there were some major
openings into Europe and the Middle East. Added Jordan to my
country list, and worked Wales, the Ukraine, Russia, Poland, and a wack
of other countries. Here are some updated pictures on how the
environment is working. There are two workstations set up there.
Jeff's and mine. I've got the Flex-Radio 5000A set up, as well as
the SPE 1KW Expert amplifier. The gentleman I talked to in Wales
today was actually the service engineer for SPE in that part of the
world. We have a G5RV up, a three band dipole, a Cushcraft AS3
beam, on a rotator at about 32 feet. We also have an 80 meter
dipole, a 40 meter dipole and a 20 meter dipole. There is a 2M -
440 antenna up as well.

Above - looking from the road access.
The two pods are welded onto the roof - there is an AS3 Yagi with a
rotator on the far end of the second pod. The propane generator
will be in one pod, the 800 amp hours of liquid ni-cads in the other.

Looking from the East into what will
become the Porch, and on the other side of the sliding glass doors, my
operating position.

Looking East - across the babbling brook,
is one of the utility poles

Looking North - if you look carefully you
can see the grass / hay starting to reseed

Looking West - you can see the SARC 'Big
Yellow' tower that is on loan to me. In addition, you can see the
500 gallon propane tank

Here you can see the propane exhaust -
and unintentionally, behind it you can see a 21 foot mast with the AS3
on it.

The Yagi in the foreground, isn't in use,
it was just the safest way to store this Yagi until we find a home for
it

Looking due East - the other two Utility
poles and if you click on the thumbnails, you should see the dipoles

To the right, the propane airtight stove.
Ben L. welded up the stand for the propane generator, which will go in
one of the pods. In the foreground, you can see two 500 foot
spools of RG8X - we're going through a wack of coax!

In the foreground you can see the
distressed leather couch. Thanks Kathy. In the background is
where the kitchen will eventually go in

Looking the other way - East - Jeff's
workstation, and the washroom / Coax Transfer station

Bill's workstation in the background -
and then the porch past the sliding glass doors. There is linoleum
in the foreground, which hasn't been installed yet. The big oak
area covers the 900 amp hours of batteries, as well as the Pro-Sine 3
Inverter / Charger. There is also storage in the banks of drawers.
The bench can be used as a sleeping platform, a work bench, or in its
current configuration, a junk collector! The four clocks show GMT,
Local, CTT and Japan local time.
There will be another workstation at this
end of the bench. The folding chairs will find a new home.
I've got some pictures to put up. They are Budweiser and
Labatt Blue Light beer posters. Some are legal, and some were not
approved. I got rid of them a few years ago, as I had a young
daughter and thought they wouldn't be appropriate. My brother's
boys enjoyed them for a number of years, and they have just found their
way back to my possession. So they will decorate the 'Man-Cave'.
I've insulated the floor in the
electrical room (soon to be a bedroom), and the washroom / Coax Transfer
room. I need to put a priority on getting the composting toilet
installed. I've had a donation of a nice area rug - thanks Gary
(red wine coloured!). Water and a kitchen install need to be on
the list, after we get the propane generator installed.
100313 - I
spent a couple of hours at the project today. Only had the 2 meter
radio on. My main goal down there today was to recharge the batteries.
I got there about 2:20 P.M. PST, and fired up the generator with a
fresh tank of gas. Running the Honda EU2000, and it is running hard.
I’ve plugged the Xantrex tri charger into the Pro-Sine 3KW inverter.
This lets the inverter manage how the power is split between running
the load and charging the 24 volt batteries.
Currently, for the 12 volt batteries,
I’m using one 150 Amp hour Gel under my desk. There are three of those
batteries, and I need to look at adding more capacity to that battery
bank. We have equipment plugged into it and running 7 x 24 (our
internet link – which isn’t yet up – but we thought it would be good to
see how the load is handled). Also, last weekend, I ran the whole
environment – radios and amplifier just off of batteries for the better
part of a day. The Pro-Sine will charge the 24 volt battery bank at
over 50 amp hours, if I could give it enough juice.
The 12 volt charger will charge at 40 amp
hours. Which it did when I first got here. It has dropped down to 10
amp hours now, after running for almost 2 hours at 20 amp hours. So the
batteries were exercised this week. The Pro-Sine is charging at up to
42 amp hours – and is slowly dropping down – now at 29 volts at 31 amp
hours.
The long term plan is to add a wind
turbine to top up the 24 volt batteries. The wind on top of the C cans
seems to be pretty constant, so maybe it will do the job – we’ll see.
There is an option I am looking into as well, where the propane
generator could be automatically started and run to top up the 24 volts
battery bank. Theoretically, I could charge the other 12 volt battery
systems from the Pro-Sine 3.0, or remotely turn them on and off. I
also want to look at solar power for the 12 volt and 24 volt battery
banks.
The next major work package for the team
is going to be getting the propane generator installed in the pod. Ben
has put a louvered escape hatch on the pod. It will be set up so that
it cannot be easily removed, but will allow hot air to rise, and vent
through the louvers. Expanded steel mesh will prevent birds from
getting in to next.
Holes will be cut in the floor of the pod
– and expanded steel put over them. This will give us a rodent proof
place for cool air make up and combustion air to get into the pods. We
will be putting steel pipes between the pods and the electrical room.
We will run our 120 volt wiring, the 12 volt wiring, and the control
cables through individual pipes. With any luck we will get this done
before the end of March. It will be really nice to come into the
project, press a button and the generator starts, and we don’t have to
haul fuel for it (it will be plumbed into the 500 gallon propane tank).
I took some pictures today, but they suck -
so will have to see if I can take down a better camera.
100220 -
Well - I've been a little remiss in keeping the web site updated.
I will get some pictures in here tomorrow or Monday. This is a
status update.
Jeff moved his equipment in there a week
or so ago. I moved my new gear in there yesterday. I spent a
good chunk of today operating from there - both as VG7G and VE7XS.
I now have my Flex 5000A, SPE 1K Expert amplifier, and peripheral
equipment located down there. We have dipole antennas up for 20,
40 and 80 Meters. We also have a G5RV up, and a triple band
dipole. We have put together two yagis, neither of which is
operating as planned (not resonant on the frequencies we want). We
picked up the Big Yellow tower from the Surrey club (thanks for the
loan) today. We will try and install it tomorrow and get either a
tri-band or mono-band yagi working on it. With any luck, we'll
also get one of the other yagis fixed as well.
Heat is in - nice, dry propane heat -
leave the shack at 55 F, and it comes up to 70 F very quickly. We
have two full operating positions working.
In service, we have a Pro-Sine 3KW Pure
Sine Wave inverter, running off of almost 900 amp hours of 24 volt
batteries (GNB Sealed Lead Acid batteries) in an air tight box vented to
the outside through the floor. In addition, we have three SLA 155
amp hour batteries under my workstation, providing 12 volts to my
workstation. We have two EU2000 Honda generators providing
temporary power as required. There is 880 amp hours of 12 volt
liquid ni-cads that haven't been brought into production yet - more work
required.
We have a propane 2.5 KW generator ready
to install - maybe tomorrow if we can get things organized well enough.
This will be a remote start, from inside the shack. Eventually, I
will tie this into the Pro-Sine 3.0 Inverter, and it will automatically
start as required. I ran the shack today on and off for about 4
hours, without running the generator. I was running up to 1 KW
into the dipoles, and racked up about 70 contacts. I did a lot of
rag chewing, so fairly high demand on the environment. After we
picked up the mobile tower, I ran the generator, and the battery banks
were almost fully charged after an hour or so.
Big Al (VA7MP), finally embarrassed me
into fixing the mobile radio problem in my car. Thanks Al - I
appreciate the push, and the help! So I have new fancy fuses in my
car wiring. I'll take some pictures and share them up shortly.
Having the station run completely off of
batteries works really well. When you unlock the containers, you
face a wall, and it has a door and a regular door lock on it. As
you step into the containers, it is looking more and more like regular
office space than the inside of two shipping containers. There are
wall light switches inside the cans. If they are painted red, they
are on 'emergency' power, and will work even when the generator is not
running. It takes about four seconds for the Inverter to sense a
load, and then it turns on. There are also plugs inside the cans
that are painted red - they operate in the same manner, they work even
if the generator isn't on.
The intent was that you could run the
stations completely off of the grid - for a protracted period of time.
The kitchen is not yet completed, but we have a counter top that we can
use. There is a propane and butane stove down there, and we have
an electronic coffee pot. We have not installed the
composting toilet yet, on the list, but hasn't been done.
|