|
111227 -
Jeff's
workstation - couple of pictures post RigRunner and Anderson PowerPoles


And
then Bill's workstation - needs some TLC and a cleanup

Here
is Ben - I told him when I took the picture that it would look like he
was standing on the bridge of a ship in the North Atlantic - wasn't far
out!

The picture above was taken one very
cold, clear morning. I noticed that the cob webs had frozen, and I
got a picture as the sun hit them. Camera phone picture - so not
very good...
111120 -
-



110921 - Finally got the Shaw High
Speed Extreme installed at one of the Farmer's shop. The tech
pulled the cable into the otter box, and we did a temporary install in
the otter box. I reconfigured the router, to be the same as the
test router we used on Saturday. Plugged it all in, tested it in
the driveway, and then at the road entrance to the driveway - not a lot
of signal strength, but full download - did a test in the driveway, and
at the road, and it was smoking!
Went to the Project, and turned up the
radio wireless modem there. Turned on my workstation, and did an
Ipconfig/renew - and bang, my workstation was on the Internet. Ran
the download test, and we tested, from the Project, higher then promised
for the package we have. Awesome!
When I conceived of Internet at the
project, I thought I would be 'borrowing' bandwidth from someone else,
and that would have required a router. Now that we have a router
at the shop, adding another one isn't such a good idea. I think we
are going to need to pick up a wireless bridge, and I think we are going
to have to wire it in the middle of the cans - not in the coax transfer
room.
We are targeting Oct 1st for the next
work party - we want to get that 20 meter monster mono-band yagi up.
It will be a lot of work. The Herefords were let back into the
field today - more green 'land mines' coming up!
110917 - Long day at the project
today. Weather started out very miserable, and then got much
better. We were working on getting the 5 band Cushcraft yagi up -
relocate the cable to an overhead carry line, and start building out the
coax cable and hard line to go to the South West telephone pole.
In addition, we wanted to get the Internet installed. It was a
very busy day, and we all hurt! Al got the 3 way fridge plumbed in
and checked out on propane - we're ready to do the 120 volts and 12 volt
DC and then we have a fridge at the project - whoo hooo!
Here are some pictures of the day.

Jeff 'kitting' up for working on the tower - safety
first always

Jay high temp silicone around the metal box that
contains the 3 way fridge

Gary getting started on the LMR600

Heat shrink tape - a dollar an inch - and worth every
penny

Jeff - hanging around - while we get things ready on
the ground


Dave - working on the 'box' that will contain the
Internet 'connectivity' stuff from the farm house

Heinz and Gary - that Heat Shrink was wicked stuff to
work with


The first of many times this antenna went up - some
challenges today with the 5 band Cushcraft

And the darn antenna down for some more checking




Jay and Jeff - cutting over the coax and control
cables to the overhead carry line

This is a massive amount of cable - individual runs
of LMR 400, LMR 600 and hard line - a lot of money ready to to into the
conduit to the antennas


Jeff - are we done yet - long day for the guy up the
tower - thanks Jeff


Dave and Al - down at the farm installing the
Internet Link - an Otter box knock off contains all of our gear - power
through the back of the box into the shop - battery, charger, control
for the high speed link to the project, and next week - the wireless WAN
router

Inside of the box - sans battery and WIFI - that is
next week

Jeff - that is one massive amount of cable ready to
go into the ground - and a lot of valuable cable!
110903 - We have been doing work
down at the project - as well as playing radio. We have been
working on the three way fridge. Ben was down there today, and he
cut in the steel frame that is going to to up tight against the C cans -
and seal the three way fridge so it doesn't leak any gasses into the C
can. I'm impressed - nice job Ben.

Ben - laying out the Air Vents for the 3
way fridge.

Here is 'insert' for the 3 way fridge.
Ben did an awesome job of cutting this in. How does he do that
(and the tradesmen don't have to answer that)! The vents are going
to be cut into this area - the holes are drilled so that Ben can see
where the vents need to be cut in.


Once the vents are set in place, we will
screw the 'box' in place, and then use high temperature silicone to seal
it in place.

Cutting out the vents.


|